EA THREE onshore construction update

Public Right of Way closure at Clappits Farm (updated 14/11/22)

Public Footpath (Ref E-537/031/0) will be closed week commencing 14th November until 5th December 2022 to enable utility works. The footpath runs between Newbourne Road/Woodbridge Road and Mill Road. This update supercedes the previously advertised closure between 26th September and 21st October, which was never implemented.

A copy of the new Notice is available here.

Public Right of Way closure at Clappits Farm (updated 14/09/22)

Public Footpath (Ref E-537/031/0) will be closed between 26th September and 21st October 2022 due to onshore construction activity relating to the East Anglia THREE Offshore Windfarm development. The footpath runs between Newbourne Road/Woodbridge Road and Mill Road. 

The Notice for the PROW closure is available here.

Paper Mill Lane chosen as preferred Construction Consolidation Site (Updated: 24/08/22)

Following the completion of site access points at three Construction Consolidation Sites (CCSs) in July, Paper Mill Lane has been chosen as the location for the installation of the full CCS. The remaining work includes the provision of office cabins, welfare, parking and storage facilities for equipment and materials.

Our contractor NKT has told us they also wish to continue work at Playford Corner and Clappits Farm, in readiness for the arrival of office cabins and associated facilities in the latter half of 2023. Work is anticipated to resume at these locations from the end of September, continuing until the end of November and will include:

  • Installation of post and wire fencing around the site perimeter
  • Stripping of topsoil to be stockpiled as earth bunds
  • Installation of silt fencing
  • Excavation for the installation of drainage
  • Installation of site hardstanding and access road

Office cabins, welfare and storage facilities will be brought to site in the latter half of 2023. Work on the installation of the onshore cables will begin in 2024.

Onshore cable corridor - CCS installation (updated 07/07/22)

Work will begin installing access points for three of our seven temporary Construction Consolidation Sites (CCSs) in July. A CCS will be used for office space, welfare, parking and the storage of equipment and materials.

The accesses will be installed off the public highway and traffic management will be installed for the safety of all road users. Following the creation of the site accesses, one CCS will be fully delivered this summer with the others following in the latter half of 2023.

Playford Corner

Bealings Road will be closed between Butts Road and Church Road between 11-16 July 2022. A diversion route will run as follows:

  • From Butts Road, the diversion route runs west to the junction with Grundisburgh Road, then north-east to Grundisburgh, east along the B1079 and west through Great Bealings.
  • From Church Road the diversion runs east through Great Bealings, north-west along the B1079 to Grundisburgh and south through Culpho to Bealings Road.

A drawing of the diversion route is available here.

Clappits Farm

Newbourne Road/Woodbridge Road will be closed south of the junction with Ipswich Road to Clappits Farm between 18-23 July 2022. Access will be provided to residents on the road, with through-traffic following an approved diversion route:

  • North of the closure the diversion will run west along Ipswich Road and then south and east along Ipswich Road to Newbourne.
  • South of the closure the diversion will run via Newbourne, west, north and then east along Ipswich Road.

A drawing of the diversion route is available here.

Public Right of Way E-537/031/0, east from Newbourne Road/Woodbridge Road to Mill Road, will also be closed between 18-25 July 2022.

The Notice for the PROW closure is available here.

Paper Mill Lane

A lane closure will be implemented on Paper Mill Lane on 25 July while a slip lane to our CCS site is created. Traffic lights are expected to be in place for up to ten days while the work is completed.

A 30mph speed limit will also be implemented on the northern end of Paper Mill Lane on 25 July while activity takes place at the site. In the event Paper Mill Lane is chosen as the location to install the CCS, the speed restriction would remain in place until the end of the construction phase in 2025.

A decision on which CCS to install will be taken at the end of the month. All CCSs will be removed at the end of the project and the land reinstated.